COST MANAGEMENT ANALYSIS WITH EARNED VALUE METHOD ON ROAD IMPLEMENTATION PROJECT IN UAIACA - QUELECAI TO OSSU BAUCAU CITY, TIMOR LESTE
Main Article Content
Agata Maria Orleans Alves*
Hanie Teki Tjendani
Esti Wulandari
Project management plays a critical role in ensuring the success of infrastructure projects like road implementations, which are essential for the development of emerging regions such as Baucau City, Timor Leste. Challenges often arise due to discrepancies between planned schedules and actual implementation, exacerbated by logistical constraints and unforeseen changes in project requirements. Effective cost management, exemplified by methods like Earned Value Management (EVM), becomes crucial in maintaining project feasibility and controlling expenditures. The purpose of this study was to analyze the cost of road implementation projects using the Earned Value Analysis Method. The method used in this study is to use the Earned Value Method with a project duration of 18 months, where the importance of the earned value analysis method is very helpful for the owner and project implementer to more easily analyze the performance of the project being carried out so as to provide benefits for the owner and project implementation. The findings revealed a project cost overrun of $205,483.12, attributed to low labor productivity and inadequate management, resulting in extended project timelines and subsequent delays in follow-up activities.
Alfathan, M. F. (2021). Penerapan Analisis Konsep Nilai Hasil di Proyek Pembangunan Sarana Prasarana Radar Pasif STT Natuna dengan menggunakan Program Primavera P6.
Anjani, A., Nugroho, M. W., Sundari, T., & Ramadhani, R. (2023). Analisis Proyek Pembangunan Jembatan Pelabuhan Patimban Menggunakan Metode Earned Value. Jurnal Sipil Sains, 13(2).
Ayatullah, M. A., Syafrudin, S., & Sarmingsih, A. (2023). Analisis Manajemen Waktu Pada Proyek Pembangunan Jalan Parang Garuda East Kawasan Industri Kendal. Jurnal Profesi Insinyur Indonesia, 1(3), 88–92.
Cahyono, B., Witjaksana, B., & Tjendani, H. T. (2022). Analisis Manajemen Risiko Pelaksanaan Proyek Pembangunan Jalan Tol Manado-Bitung Seksi 2 STA 14+ 067–39+ 700. Senakama: Prosiding Seminar Nasional Karya Ilmiah Mahasiswa, 1(1), 57–66.
Dharmawan, R. D., Safarizki, H. A., & Firdausi, A. A. (2023). Evaluasi Efektivitas Keputusan Addendum Proyek Terhadap Waktu Pekerjaan Proyek Berbasis Earned Value Method. J@ Ti Undip: Jurnal Teknik Industri, 18(1), 51–61.
Gerung, J. O., Dundu, A. K. T., & Mangare, J. B. (2016). Analisa Penerapan Manajemen Waktu Pada Pembangunan Jaringan Daerah Irigasi Sangkup Kiri. Jurnal Sipil Statik, 4(7).
Nono, Y., Pratasis, P. A. K., & Malingkas, G. Y. (2019). Analisis Metode Nilai Hasil Terhadap Waktu Dan Biaya Pada Proyek Office and Distribution Center, AIRMADIDI, MINAHASA UTARA-MANADO. Jurnal Sipil Statik, 7(11).
Nufah, Y. W., Yanti, G., & Lubis, F. (2019). Analisis Proyek Dengan Metode Earned Value Concept (Studi Kasus Pada Proyek Pembangunan Jalan Tol Ruas Pekanbaru–Dumai Seksi 2 Sta. 9+ 500–33+ 600). Prosiding Seminar Nasional Cendekiawan, 1–59.
Pabalik, C. P., Walangitan, D. R. O., & Pratasis, P. A. K. (2018). Analisis Nilai Hasil Terhadap Waktu Pada Proyek Konstruksi.(Studi Kasus: Pembangunan Gedung Laboratorium Fakultas Teknik Universitas Sam Ratulangi). Jurnal Sipil Statik, 6(11).
Permana, A. P. (2022). Penerapan Analisis Konsep Nilai Hasil Pada Proyek Pembangunan Gedung Dinas Perhubungan Surakarta Menggunakan Aplikasi Primavera P6.
Sakinah, K. N. (2021). Analisis Kinerja Biaya Dan Waktu Menggunakan Metode Earned Value Dan Earned Schedule Pada Proyek Pembangunan Villa Pasir Angin Puncak-Bogor. Akselerasi: Jurnal Ilmiah Teknik Sipil, 3(1).
Sari, H. M., Hendriyani, I., & Widyaningrum, A. E. (2021). Earned Value Analysis pada Proyek Pembangunan Gedung Arsip Kantor BPN: Earned Value Analysis of BPN Office Archives Building Projects. Jurnal Ilmiah Teknik Sipil TRANSUKMA, 3(2), 154–167.
Tangtobing, R. F. F., & Waty, M. (2023). Penerapan Metode Earned Value Dan Earned Schedule Pelaksanaan Proyek Rumah Sakit X Di Bandung. JMTS: Jurnal Mitra Teknik Sipil, 237–248.
Wicaksono, R. M. B. (2021). Analisis kinerja biaya dan waktu menggunakan metode earned value pada Proyek Pembangunan Infrastruktur Laboratorium Tradisional Food GMP Facility (Paket 3). Akselerasi: Jurnal Ilmiah Teknik Sipil, 3(1).
Winarto, T. J. (2021). Analisis durasi proyek x dengan metode earned schedule. Jurnal Dimensi Pratama Teknik Sipil, 10(1), 82–89.