COST AND TIME PERFORMANCE ANALYSIS USING EARNED VALUE METHOD OF WHEAT SILO & PELLET SILO STRUCTURE REPAIR PROJECT PHASE 3 PT. ISM BOGASARI SURABAYA
Main Article Content
Edwin Octavianto Saputra*
Haris Muhammadun
Risma Marleno
The wheat silo and pellet silo structure repair project phase 3 by PT. ISM Bogasari Surabaya is an annual infrastructure maintenance and strengthening activity to support the smooth production process. For this reason, it is very important to be completed on time according to the contract in order to proceed to the next stage of repair and not experience delays that can result in cost overruns. In this study using EVM (Earned Value Method) analysis in overcoming these problems to determine the cost and time performance of implementation as the project progresses and the indicators used in the analysis include SV (Schedule Variance), CV (Cost Variance), SPI (Schedule Performance Index), CPI (Cost Performance Index), which aims to obtain the results of the calculation of ETC (Estimated To Complete) & EAC (Estimated At Complete) in the project completion cost forecast. While ETS (Estimated Temporary Schedule) and EAS (Estimated All Schedule) for project completion time forecast. Based on the results of the cost & time performance analysis carried out up to week 48, the CPI> 1 value shows that the project is experiencing savings and for time performance shows the SPI < 1 value, which means that the project is experiencing delays.
Aditama, R., & Witjaksana, B. (2021). Analisis Biaya dan Waktu Menggunakan Metode EVM (Earned Value Method) Pada Proyek Konstruksi (Studi Kasus Pada Proyek Pembangunan Gedung Laundry …. Junal Universitas 17 Agustus 1945 Surabaya, 45, 1–15.
Ariana, I. K. A., & Lestari, D. A. (2023). Analisis kinerja proyek optimalisasi SPAM Gatak Kabupaten Sukoharjo dengan metode earned value. Journal of Integrated System, 6(1), 87–102.
Arifin, M. F. A., Sarifatuzzuhriyah, M., & Liu, S. S. (2023). Cost And Time Control Analysis With Earned Value Method In The Mrt-Hub Building Construction. Jurnal Teknik Sipil Dan Perencanaan, 25(1), 90–99.
Asmoro, M. R., Witjaksana, B., & TJendani, H. T. (2023). Cost And Time Analysis Using Earned Value Method Construction Of Upbjj Building Open University Of Surabaya Phase Ii. Asian Journal Of Engineering, Social And Health, 2(12), 1799–1810.
Bonny, A., Oetomo, W., & Marleno, R. (2022). Analysis Of Time And Cost Control Using The Earned Value Method In Well Pad Hilling And Compacting Work In The Pt. Pertamina Hulu Rokan Riau Province. Devotion: Journal Of Research And Community Service, 3(14), 2802–2814.
Ervianto, W. I. (2023). Manajemen proyek konstruksi. Penerbit Andi.
Farhan, M., Hajji, A. M., & Larasati, A. (2021). Physical progress analysis of structure works using earned value management integrated with artificial neural network. AIP Conference Proceedings, 2447(1).
Febriantoro, M. B., Susanto, S., & Siswanto, E. (2022). Meminimalisir Keterlambatan Waktu dan Pembengkakan Biaya Proyek Pembangunan Gedung Kecamatan Dongko, Trenggalek dengan Metode Nilai Hasil (Earned Value Method). Jurnal Manajemen Teknologi & Teknik Sipil, 5(1), 104. https://doi.org/10.30737/jurmateks.v5i1.2881
Husein, A., & Perencanaan, M. P. (2011). Penjadwalan, dan Pengendalian Proyek (Edisi Revisi). Yogyakarta: Andi Offset.
Indriani, A. M., Utomo, G., & Rizqy, M. (2022). Analisis Kinerja Waktu Dan Biaya Proyek Konstruksi Dengan Metode Earned Value Analysis. Jurnal GeoEkonomi, 13(2), 128–137.
Irniawan, D., Oetomo, W., & Marleno, R. (2024). Earned Value Analysis For Cost And Time Efficiency On The Bondowoso Polije Campus Administration Building Project. Journal Of Humanities, Social Sciences And Business, 3(2), 486–497.
Kamandang, Z. R. (2022). The Project Performance Evaluation of Road Construction Project Using Earned Value Method. CI-TECH, 3(1).
Marleno, R., Surjokusumo, S., Oetomo, W., Setiawan, M. I., & Abdullah, D. (2018). The influence of stakeholder factors affecting the success of construction projects in Indonesia. Journal of Physics: Conference Series, 1114(1), 12135.
Nurkholis, N., & Abduh, M. (2022). Analisis cost varians dan schedule varians menggunakan metode earned value pembangunan kantor kelurahan di kota pasuruan. Seminar Keinsinyuran Program Studi Program Profesi Insinyur, 2(1). https://doi.org/10.22219/skpsppi.v3i1.5046
Oetomo, W., Priyoto, P., & Uhad, U. (2017). Analisis Waktu dan Biaya dengan Metode Crash Duration pada Keterlambatan Proyek Pembangunan Jembatan Sei Hanyu Kabupaten Kapuas. Media Ilmiah Teknik Sipil, 6(1), 8–22.
Pabalik, C. P., Walangitan, D. R. O., & Pratasis, P. A. K. (2018). Analisis Nilai Hasil Terhadap Waktu Pada Proyek Konstruksi.(Studi Kasus: Pembangunan Gedung Laboratorium Fakultas Teknik Universitas Sam Ratulangi). Jurnal Sipil Statik, 6(11).
Putra, H. R., Koespiadi, K., & Oetomo, W. (2024). Cost And Time Analysis Using Methods Earned Value. Asian Journal of Engineering, Social and Health, 3(1). https://doi.org/10.46799/ajesh.v3i1.204
Salsabila, M. D. N., Puspita, I. A., & Widyasthana, S. (2022). The Project Performance Evaluation of PLBN Project Using Earned Value Management Method. International Journal of Innovation in Enterprise System, 6(01), 61–73.
Utomo, B. S., Wibowo, K., & Soedarsono, S. (2022). Earned Value Concept as a Method to Analyze Cost and Time Control. JACEE (Journal of Advanced Civil and Environmental Engineering), 5(2), 103–112.
wahyu santoso. (2017). Analisis Percepatan Proyek Menggunakan Metode Crashing Dengan Penambahan Jam Kerja Empat Jam Dan Sistem Shift Kerja. Tesis, 1, 89.
Widiasanti, I., Rochadi, D., Fridestu, A., & Lenggogeni, L. (2019). Identification of the inhibiting factors for skilled labour in the construction sector to obtain competency certification. Journal of Physics: Conference Series, 1402(2). https://doi.org/10.1088/1742-6596/1402/2/022025