Analysis of the Probability of Successful Completion Time of the Penganten-Ngampal Road Reconstruction Project Using the PERT Method
Main Article Content
Akmal Puguh Al-Putro*
Laksono Djoko Nugroho
Haris Muhammadun
Infrastructure project delays are often a major challenge in the construction industry, including the Penganten - Ngampal Road Reconstruction project which experienced a 50-day delay from the initial target. This problem is caused by the uncertainty of external factors such as weather and limited resources. This research aims to calculate the probability of success of project completion time using quantitative descriptive method with Program Evaluation and Review Technique (PERT) approach. This method involves three estimates, namely optimistic, most likely, and pessimistic times to evaluate the average duration and critical path of the project. The data used consisted of project reports, field observations, and calculations using POM-QM software. The analysis shows that the project critical path consists of activities A, C, D, E, and F with a total duration of 60 days. The probability of completing the project within 60 days reached 98.21%, showing the effectiveness of the PERT method in managing time uncertainty.
Agrawal, A., & Halder, S. (2020). Identifying factors affecting construction labour productivity in India and measures to improve productivity. Asian Journal of Civil Engineering, 21(4). https://doi.org/10.1007/s42107-019-00212-3
Astari, N. M., Subagyo, A. M., & Kusnadi, K. (2022). Perencanaan Manajemen Proyek Dengan Metode Cpm (Critical Path Method) Dan Pert (Program Evaluation and Review Technique). Jurnal Konstruksia, 13(1), 164–180. https://doi.org/10.24853/jk.13.1.164-180
Dimyati, H., & Nurjaman, K. (2014). Manajemen Proyek (1st ed.). Pustaka Setia.
Hasnah, R. F., & Herwanto, D. (2023). Evaluasi Pelaksanaan Proyek di PT Maswindo Bumi Mas Branch Subang Menggunakan Metode CPM dan PERT. Jurnal Serambi Engineering, 8(3), 6168–6179. https://doi.org/10.32672/jse.v8i3.6120
Husna, R. A., Ilmiyah, N. F., & Resti, N. C. (2022). Implementasi CPM dan PERT dalam Memprediksi Durasi serta Biaya Pembangunan Musala Al-Ikhlas di Kotawaringin Barat. Journal Focus Action of Research Mathematic (Factor M), 5(1), 97–109. https://doi.org/10.30762/f_m.v5i1.633
Nanda, M. P., Kurniawati, M., & Riswanto, S. (2023). Penggunaan Metode Project Evaluation Review Technique (PERT) dalam Evaluasi Perencanaan Penjadwalan Proyek. Jurnal Teknik Sipil, 17(3), 163–173. https://doi.org/10.24002/jts.v17i3.7181
Puspitasari, Y. E., Oktorully Tampubolon, H., Fajrin, A. N., Sulistiyati, T. D., & Hardoko, H. (2023). Penghambatan α-Glucosidase Oleh Flavonoid dari Ekstrak Etil Asetat Daun Mangrove Sonneratia alba Sebagai Antidiabetes Melalui Penambatan Molekuler. Indonesian Journal of Fisheries Science and Technology Available, 19(1), 15.
Rani, H. A. (2016). Manajemen Proyek Konstruksi (1st ed.). Deepublish.
Srinivasu, B., Professor, A., & Srinivasa Rao, P. (2013). Infrastructure Development and Economic growth: Prospects and Perspective. Journal of Business Management & Social Sciences Research, 2(1).
Uktolseja, A. M., Wullur, M., & Karuntu, M. M. (2023). Evaluasi Pelaksanaan Proyek Menggunakan Metode PERT Dan CPM (Studi Kasus: Preservasi Jalan Tolango-Paguyaman, Tolango-Bulontio). LPMM Bidang EkoSosBudKum (Ekonomi, Sosial, Budaya Dan Hukum), 6(2), 1079–1090.