ANALYSIS OF TIME AND COST PERFORMANCE IN THE COMPLETION OF THE CONSTRUCTION PROJECT FOR THE REGIONAL DISASTER MANAGEMENT AGENCY (BPBD) BUILDING COMPLEX IN PASURUAN REGENCY, BUDGET YEAR 2023
Main Article Content
Bagus Cahyono*
Risma Marleno
Wateno Oetomo
In the construction project of the Pasuruan Regency BPBD building complex, which is currently still ongoing, has experienced problems related to the schedule for the implementation of its activities. The problem in question is the delay in the schedule for the implementation of its activities, where the results of the progress realization are not in accordance with the schedule plan, through this writing an evaluation is carried out related to performance in the field through an approach using. The data analysis process is carried out by calculating analysis indicators including BCWS, BCWP and ACWP, the calculation of cost indicators consists of calculating the CV value, Cost Performance Index (CPI), ETC and EAC, and also calculating related to time indicators including calculating the SV value, Time Performance Index (SPI) and also calculating the time requirements / Estimated time (TE) in project completion. Based the results of calculation / data analysis that has been carried out, the Cost Performance Index value CPI> 1 is obtained, and the SPI Time Performance Index value < 1, indicating that the realization cost is still below the plan cost with the achievement of progress realization which is also still below the plan schedule. while for the ETC value of project completion of Rp.2,148,176,877,000..148,176,877.17 with an EAC value of Rp.16,624,276,448.77 from the total contract value of Rp. 18,898,770,576.77. and related to the estimated time requirement for project completion (TE) obtained a time of 220.75 ⁓ 221 days, 11 days later than the time provided 210 days.
Adinata,Surya dan Akbar Alfa 2020. ”Penerapan Metoda Konsep Nilai Hasil (Earned Value Concept) Pada Proyek Peningkatan Jalan Aspal Di Lokasi F4 (Sungai Sirih)”.Selodang Mayang :Jurnal Ilmiah Badan Perencanaan Pembangunan Daerah Kabupaten Indragiri Hilir 6(2) : 109.doi : 10.47521 / selodangmayang.v6i2.171.
Castollani, A., Puro, S., Maiko, *, & Dewa, L. (2020). Analisis Biaya dan Waktu pada Proyek Apartemen Dengan Metode Earned Value Concept. 3(1).
Devaux, S. A. (2014). Managing Projects as Investments Earned Value to Business Value.
Hanie Teki Tjendani, Nuri Maulidi, Miftahul Huda (2021). Analisis Biaya dan Waktu Pada Pembangunan Gedung Trauma Center Dan Intensive Care Tahap VI RSUD Dr.Soedono Madiun Dengan Metode Earned Value
Iman Soeharto. (1999).Manajemen-proyek dari konseptual sampai operasional: Vol. Edisi Kedua.
Izeul,Muhammad,Retno Indryani,Jurusan Teknik Sipil,FakultasTeknik Sipil,Institute Teknologi Sepuluh November,Jl.Arief Rahman Hakim,E-mail Retnoiceitsacid,and A.Kinerja Proyek.2015.”Metode Earned Value untuk Analisa Kinerja Biaya Pembangunan Condotel De Vasa Surabaya”.Jurnal Teknik ITS 4(1).
Mandiyo Priyo, T. Z., & Teknika, S. (2017).Penerapan Metode “Earn Value” Dan “Project Crashing” Pada Proyek Konstruksi: Studi KasusPembangunan Gedung IGD RSUD Sunan Kalijaga, Demak (The Application Of Earn Value Methode And Project Crushing Of Project Crushing: Case Study Construction Building Of Igd Rsud Sunan Kalijaga, Demak) (Vol. 20, Issue 1).
Muniroh, rifatul, & Buyang, C. (2021). Pengendalian Biaya Dan Waktu Dengan Earned Value Concept Pada Proyek Penataan Bangunan. Jurnal Simetrik, 11(1).
Nugroho,Wisnu Abiarto.2019.”Analisis Pengaruh keterlambatan Terhadap Biaya Menggunakan Earned Value Concept (Pada Proyek Jetty di Pulau Waibalun,Flores Timur)”.3:25-40.
Rifqi Auzan N, D. R. S. S. F. K. (2017). Pengendalian Biaya Dan Waktu Proyek Dengan Metode Konsep Nilai Hasil (Earned Value) (Vol. 6). http://ejournal-s1.undip.ac.id/index.php/jkts
Romadhonnia, N., Ferdaus, M., Aulady, N., & Nuciferani, F. T. (2018). Pengukuran Kinerja Waktu Dan Biaya Proyek Pembangunan Jetty Menggunakan Metode Earned Value.
Wahyuni, Elvi, and Bambang Hendrawan. 2018.“Analisis Kinerja Proyek ‘Y’ Menggunakan Metode Earned Value Management (Studi Kasus Di PT Asian Sealand Engineering).” Journal of Applied Business Administration 2(1):60–78. doi: 10.30871/jaba.v2i1.784.
Zakariyya,Bagus,Ahmad Ridwan,and Suwarno Suwarno.2020.
”Analisa Biaya dan Jadwal Proyek Pembangunan Gedung Dinas Kesehatan Kabupaten Trenggalek dengan Metode Earned Value.”Jurnal Manajemen Teknologi & Teknik Sipil 3(2) : 362.doi : 10.30737/jurnateks.v3i2.1197