TIME DELAY ANALYSIS USING CRITICAL PATH METHOD (CPM) (Case Study: Kerobokan Bali Parking Building Construction Project)
Main Article Content
Dwi Cahyani Putri*
Budi Witjaksana
Hanie Teki Tjendani
Parking Building is a structure specifically built for vehicle parking. Kerobokan Bali Parking Building is one such structure that utilizes steel as its main material. With dimensions of 13.97 meters in height, 32.8 meters in width, and 16.18 meters in length, this building had a planned construction duration of 259 calendar days starting from July 2023. The parking building experienced delays due to flooding in the basement area, necessitating time acceleration analysis using the CPM method. This thesis employs the CPM method to identify critical path activities. Once the critical paths are identified, a crashing program analysis will be conducted, involving an alternative such as overtime work with a duration of 4 hours. Based on the analysis using the CPM method, it was found that 75 activities are critical, listed in Microsoft Project rows 368-369-370-372-380-381-382-383-384-385-387-388-389-390-392-393-394-395-398-399-400-402-403-404-406-412-415-416-417-419-420-421-422-424-425-426-427-428-430-431-432-433-435-436-437-438-441-442-443-445-471-472-473-475-476-477-479-526-527-528-530-535-621-628-629-630-633-634-635-638-639-640-643-644.
Abadiyah, S., Mu’min, M. A., & Julianto, T. D. (2020). Analisa Perbandingan Waktu Penjadwalan Proyek Dengan Metode CPM (Critical Path Method) Dan PERT (Program Evaluation And Review Technique). Structure, 2(2), 72–79.
Abdurrasyid, A., Luqman, L., Haris, A., & Indrianto, I. (2019). Implementasi metode PERT dan CPM pada sistem informasi manajemen proyek pembangunan kapal. Khazanah Informatika: Jurnal Ilmu Komputer Dan Informatika, 5(1), 28–36.
Akhir, T. (2019). Analisis Crash Program Menggunakan Microsoft.
Anwar, F. H. (2019). Analisis Crash Program Menggunakan Microsoft Project Pada Peningkatan Jalan SP. Lago-Sorek I Kabupaten Pelalawan. Universitas Islam Riau.
Astari, N. M., Subagyo, A. M., & Kusnadi, K. (2022). Perencanaan Manajemen Proyek dengan Metode CPM (Critical Path Method) dan PERT (Program Evaluation and Review Technique). Konstruksia, 13(1), 164–180.
Aulia, S., & Cipta, H. (2023). Network Planning Analysis Using CPM and PERT Methods on Optimization of Time and Cost. Sinkron: Jurnal Dan Penelitian Teknik Informatika, 7(1), 171–177.
Husna, R. A., Ilmiyah, N. F., & Resti, N. C. (2022). Implementasi CPM dan PERT dalam Memprediksi Durasi serta Biaya Pembangunan Musala Al-Ikhlas di Kotawaringin Barat. Journal Focus Action of Research Mathematic (Factor M), 5(1), 97–109.
Jaya, A. A., Yakin, K., & Bustamin, M. O. (2019). Kajian Pengaruh Percepatan Waktu Pekerjaan Konstruksi Terhadap Biaya Proyek Bess Mansion Apartement Surabaya. Surabaya: Universitas Dr. Soetomo.
Julian, D. M., Sutrisno, S., & Basri, A. A. (2023). Penerapan Metode CPM dan PERT pada Proyek Pembangunan Drainase di Perum Cengkong guna Mempercepat Waktu Penyelesaian (Studi Kasus: CV XYZ). Jurnal Serambi Engineering, 8(1).
Khozinati, I. A. (2021). Perencanaan Dan Pengendalian Proyek Dengan Metode Cpm (Critical Path Method) Di Pt Ghani Sejahtera Abadi. Scientific Timeline, 1(2), 108–116.
Maarif, M. (2021). Analisa Penjadwalan Proyek Dengan Metode PERT Dan CPM Pada Pembangunan Gedung Hotel Di Sidoarjo. Universitas Muhammadiyah Surabaya.
Mulia, T. N., & Candra, R. (2023). Analisis Penjadwalan Proyek Menggunakan Critical Path Method (CPM) Studi Kasus pada Pembangunan Gapura Taman Hutan Lindung Kota Langsa. Jurnal Penelitian Ekonomi Akuntansi (JENSI), 7(1), 82–90.
Perdana, S., & Rahman, A. (2019). Penerapan Manajemen Proyek dengan Metode CPM (Critical Path Method) pada Proyek Pembangunan SPBE. Amaliah: Jurnal Pengabdian Kepada Masyarakat, 3(1), 242–250.
Prabowo, H. (2020). Optimalisasi Project Management Pada Pt. Cipta Ekatama Nusantara Menggunakan Metode Cpm/Pert Dalam Pembangunan Perumahan Cendana Sawangan Regency. Optimalisasi Project Management Pada Pt. Cipta Ekatama Nusantara Menggunakan Metode Cpm/Pert Dalam Pembangunan Perumahan Cendana Sawangan Regency.
Purwantoro, A., Suhin, K. J., & Nuswantoro, W. (2022). Pengendalian Proyek Konstruksi Gedung Menggunakan Critical Path Method (CPM) dan Earned Value Method (EVM). Jurnal Teknika: Jurnal Teoritis Dan Terapan Bidang Keteknikan, 5(2), 65–72.
Putra, Y. E., & Gandhi, H. K. (2019). Analisis Jalur Kritis pada Proyek Relokasi Mesin Flexo dengan Metode CPM dan PERT. Jurnal InTent: Jurnal Industri Dan Teknologi Terpadu, 2(1), 65–75.
Safitri, E., Basriati, S., & Hanum, L. (2019). Optimasi Penjadwalan Proyek Menggunakan CPM Dan PDM (Studi Kasus: Pembangunan Gedung Balai Nilah Dan Manasik Haji Kua Kecamatan Kateman Kabupaten Indragiri Hilir). Jurnal Sains Matematika Dan Statistika, 5(2).
Santika, D., Lestari, S. P., & Barlian, B. (2022). Project Scheduling Analysis With CPM PERT Method (Case Study on Tasikmalaya City Swasana Village Restaurant Project). Journal of Indonesian Management, 2(3), 599–610.
Siregar, A. C., & Iffiginia, I. (2019). Penggunaan critical path method (CPM) untuk evaluasi waktu dan biaya pelaksanaan proyek. Teknika: Jurnal Sains Dan Teknologi, 15(2), 102–111.
Susilowati, E., & Widayati, R. (2023). Penjadwalan Kereta Api Daop 8 Surabaya Menggunakan Aljabar Max Plus.
Sutrisno, Audi, Pramudya, R. E. L. (2023). Implementasi Metode CPM , Crashing dan PERT Pada Penjadwalan Proyek Pembangunan Masjid dan Asrama Yatim Piatu Barokah Amanah Mustaqbal. Jurnal Serambi Engineering, VIII(2), 5390–5400.
Syaputra, I. (2019). Analisa Penjadwalan Pelaksanaan Pekerjaan Proyek Dengan Metode CPM Dan PDM Pada Peningkatan Jalan Sei Pakning (Km 130) – Teluk Masjid – Simpang Pusako Kabupaten Siak. Km 130.
Ulfa, S., & Suhendar, E. (2021). Implementasi Metode Critical Path Method Pada Proyek Synthesis Residence Kemang. Jurnal Optimasi Teknik Industri (JOTI), 3(1), 1–6. https://doi.org/10.30998/joti.v3i1.4167
Wibowo, P., & Rozy, N. (2020). Analisis Manajemen Konstruksi Pembangunan Gedung Rawat Inap Kelas Iii Rsud Waled Kabupaten Cirebon. Jurnal Konstruksi Dan Infrastruktur: Teknik Sipil Dan Perencanaan, 9(2).
Yaqin, H. N., Tjendani, H. T., & Witjaksana, B. (2023). Analysis of The Acceleration of Time and Cost of Implementing Building Construction Projects Using The Critical Path Method (CPM) Method. Devotion Journal of Community Service, 4(2), 336–346.
Yuliarty, P., Anggraini, R., & Wastiono, T. (2020). Penjadwalan Proyek Mesin Auto Assembly Membrane Regulator Valve Di Pt. Omg Metode Critical Path Method (CPM). Industri Inovatif: Jurnal Teknik Industri, 10(1), 21–31.