TIME ACCELERATION ANALYSIS USING THE TIME COST TRADE OFF METHOD ON THE WHEAT SILO AND PELLET SILO STRUCTURE REPAIR PROJECT PHASE III IN SURABAYA
Main Article Content
Maria Junita Klau*
Sajiyo
Hanie Teki Tjendani
The wheat silo and pellet silo structural repair project Phase III in Surabaya holds great significance for the wheat flour processing industry in Indonesia. PT Indofood Sukses Makmur Tbk Bogasari Surabaya Division, as one of the leading wheat flour producers, required structural repairs on both silos to ensure the smooth operation of the plant and the quality of the final product. Given the importance of time and cost in the success of this project, an effective approach to time and cost management was essential. The project necessitates proper project management to avoid delays and cost overruns, with a budget of IDR 28,011,000,000 and an estimated duration of 455 calendar days. This research employs the Time Cost Trade Off (TCTO) method to analyze options for accelerating project time by considering additional costs that may arise. Microsoft Project software is utilized to identify the critical path, allowing project managers to focus on activities with the greatest impact on the overall schedule. The results indicate that the critical path of the project includes activities such as mobilization and demobilization, administration and reporting, work safety, and repair of the old grain silo. By using TCTO, the project completion time can be accelerated to 359 days from 455 days, reducing the duration by 21.10%.
Abdilah, M. T., Puspita, I. A., & Tripiawan, W. (2021). Perancangan Waktu Dan Biaya Proyek Rehabilitasi Sekolah Menggunakan Metode Cpm Dan Time Cost Trade Off. EProceedings of Engineering, 8(6).
Abdillah, M. G., & Kurniawan, S. (2022). Analisis Metode Time Cost Trade Pada Pembangunan Perpustakaan Iain Metro. JUMATISI: Jurnal Mahasiswa Teknik Sipil, 3(1), 211–218.
Afrizal, A. I. (2018). Time Cost Trade Off Analisys Untuk Pengoptimalan Waktu dan Biaya Proyek (Studi Kasus: Pembangunan UPT Puskesmas Karangpucung).
Akbar, Y. R. (2022). Penentuan Jalur Kritis untuk Manajemen Proyek (Studi Kasus Pembangunan Jalan Selensen-Kota Baru-Bagan Jaya). Jurnal Pustaka Manajemen (Pusat Akses Kajian Manajemen), 2(1), 6–13.
Anggraeni, D. N., Nugroho, M. W., & Sumarsono, S. (2019). Optimasi Waktu dan Biayacrashing dengan Menggunakan Metode Time Cost Trade Off. Civilla: Jurnal Teknik Sipil Universitas Islam Lamongan, 4(2), 310–317.
Ariesty, A., & Nauval, M. R. (2020). Analisis Penerapan Metode Jalur Kritis pada Proyek Pembangunan Gedung Pengelolaan RTH Cangehgar. JTERA (Jurnal Teknol. Rekayasa), 5(1), 2019–2025.
Ashari, N. F. (2023). Analisis optimasi waktu dan biaya proyek dengan metode time cost trade off dan fast track pada pekerjaan penanganan longsor. Jurnal Proyek Teknik Sipil, 6(2), 21–29.
Burhanudin, M. S. (2022). Analisis Percepatan Waktu Pada Pekerjaan Sipil Proyek Pembangunan Lpg Refrigerated Dengan Menggunakan Metode Critical Path Method (Cpm) Dan Time Cost Trade Off (TCTO). Universitas Islam Sultan Agung.
Fazri, M., Widiastuti, M., & Jamal, M. (2020). Analisis Percepatan Waktu Dengan Menggunakan Metode Time Cost Trade Off Pada Proyek Pembangunan Rusun 1 Kota Samarinda Kalimantan Timur. Teknologi Sipil: Jurnal Ilmu Pengetahuan Dan Teknologi, 3(2), 1–14.
Hermansyah, H., Umar, T. D. J., & Rasdiati, R. (2022). Pemanfaatan Bonggol Jagung Sebagai Bahan Tambah Dalam Campuran Beton. Jurnal Kacapuri: Jurnal Keilmuan Teknik Sipil, 5(1), 131–139.
Mariani, R., & Witjaksana, B. (2019). Analisis Crashing Time Menggunakan Ms-Project Dalam Pelaksanaan Pekerjaan Pada Proyek Peningkatan Jalan.”. SpTS: Jurnal Spesialis Teknik Sipil.
Nugroho, D., Marleno, R., & Tjendani, H. T. (2023). Optimasi Waktu Dan Biaya Proyek Revitalisasi Pasar Kraton Kota Tegal. Jurnal Spesialis Teknik Sipil (JSpTS), 3(1), 24–41.
Pramesti, H. R., & Listyawan, A. B. (2023). Analisa Pengendalian Waktu dengan Metode Critical Path Method (CPM) pada Proyek Pembangunan Pondok Iqro’, Surakarta. Prosiding Seminar Nasional Teknik Sipil UMS, 560–566.
Pratiwi, R., Devi, S. M., Marini, A., & Sari, H. M. (2022). Optimasi Waktu Dan Biaya Dengan Metode Time Cost Trade Off (Tcto) Pada Proyek Penambahan Bangunan Pasar Rakyat: Time And Cost Optimization Using The Time Cost Trade Off Method In The People’s Market Additional Building Project. Jurnal Ilmiah Teknik Sipil TRANSUKMA, 4(2), 93–105.
Sulistyo, A. B., & Al Fikri, M. (2021). Analisis Optimalisasi Waktu Dan Biaya Proyek Konstruksi Menggunakan Metode Time Cost Trade Off. Jurnal Intent: Jurnal Industri Dan Teknologi Terpadu, 4(1), 25–40.
Sulistyo, A. B., Kusdianto, A., & Wirawati, S. M. (2023). Analisis Manajemen Proyek dengan Sistem Umbrella Contract Menggunakan Metode Time Cost Trade Off (Studi Kasus: PT Jaya Inti Teklindo). Jurnal Penelitian Dan Aplikasi Sistem Dan Teknik Industri (PASTI), 17(1), 43–57.
Ulfa, S., & Suhendar, E. (2021). Implementasi Metode Critical Path Method Pada Proyek Synthesis Residence Kemang. Jurnal Optimasi Teknik Industri (JOTI), 3(1), 1–6. https://doi.org/10.30998/joti.v3i1.4167
Vebiola, N. E., & Waskito, J. P. H. (2020). Analisis Optimasi Waktu Dan Biaya Dengan Metode Time Cost Trade Off (Studi Kasus: Proyek Pembangunan Basement Kawasan Balai Pemuda). Axial: Jurnal Rekayasa Dan Manajemen Konstruksi, 8(2), 113–120.
Waney, E. V. Y., & Ruitan, S. M. (2022). Perencanaan Waktu dan Penjadwalan Pelaksanaan Proyek Pembangunan Rusun TNI di Minahasa Utara. Prosiding Seminar Nasional Produk Terapan Unggulan Vokasi, 1(1), 290–295.
Zanri, I. F., Santosa, A. W. B., & Mulyatno, I. P. (2023). Optimalisasi Penjadwalan Ulang Perbaikan Kapal Hiu Macan Tutul 02 dengan Menggunakan Metode CPM. Jurnal Teknik Perkapalan, 11(1), 72–78.