COMPARATIVE ANALYSIS OF ACCELERATION ALTERNATIVES FOR THE DRAINAGE CHANNEL PROJECT ON XYZ STREET USINGTHE TIME-COST TRADE-OFF (TCTO) METHOD
Main Article Content
In response to the increasing occurrence of rain, the city government is actively striving to mitigate urban flooding by enhancing the drainage system. Collaboration with contracted construction firms is central to this endeavor, although it is not without its challenges, including community opposition driven by concerns over potential disruptions and limited financial resources among contractors. This study adopts the Critical Path Method (CPM) and Microsoft Project software, supplemented with the Time Cost Trade Off (TCTO) method to expedite project completion, emphasizing a comprehensive evaluation that encompasses both time and financial aspects. Notably, the analysis identifies the most feasible acceleration opportunity within the excavation of ordinary soil for construction, with original plans indicating a cost of Rp. 60,818,919 over a 40-day period. Three alternatives are considered: (1) overtime labor, incurring Rp. 65,520,000, with a 34-day duration; (2) increased workforce, incurring Rp. 68,000,000, with a 34-day duration; and (3) introducing a new addendum for the replacement of manual excavation with heavy machinery, incurring Rp. 37,440,000, with a 16-day duration. In conclusion, this study provides a comprehensive strategy for accelerating the urban drainage project, considering the critical path, time-cost trade-offs, and cost-benefit factors, highlighting the significance of selecting the most cost-effective alternative while addressing community concerns and resource limitations in flood risk mitigation efforts.
Ariyanti, A. A. dan S. (2018). Analisis Penjadwalan Proyek New Product Development Menggunakan Metode Pert Dan Cpm. Jurnal Ilmiah Teknik Industri, 6(1), 63–70. https://journal.untar.ac.id/index.php/industri/article/view/3025
Dedy Asmaroni, A. F. (2019). Analisis Percepatan Durasi Terhadap Pekerjaan Proyek Konstruksi Time Cost Trade Off Method (Studi Kasus : Pembangunan Gedung Dinas Perdagangan Dan Perindustrian Kabupaten Sampang). Jurnal Rekayasa Tenik Sipil Universitas Madura, 4(2), 2–8. http://ejournal.unira.ac.id/index.php/jurnal_rekayasa_teknik_sipil/article/view/786
Fazri, M., Widiastuti, M., & Jamal, M. (2017). Analisis Percepatan Waktu Dengan Menggunakan Metode Time Cost Trade Off Pada Proyek Pembangunan Rusun 1 Kota Samarinda Kalimantan Timur (Studi Kasus : Rusun 1 Kota Samarinda Kalimantan Timur) Penyusunan Jaringan Kerja dengan CPM. JURNAL TEKNOLOGI SIPIL, (14), 1–14. https://e-journals.unmul.ac.id/index.php/TS/article/view/3253
Guntur Fathoni, R., & Handayani, F. (2016). Analisis Percepatan Proyek Menggunakan Metode Time Cost Trade Off Dengan Penambahan Jam Kerja Lembur Optimum (Studi Kasus: Proyek Pembangunan Gedung Rawat Inap Kelas Iii Dan Parkir (Tahap Lanjutan) Rsud Dr. Moewardi, Surakarta). In e-Jurnal
Matriks Teknik Sipil: Vol. Desember 2 (Issue 7). https://jurnal.uns.ac.id/matriks/article/view/37042
Heru Nur Yaqin, Hanie Teki Tjendani, & Budi Witjaksana. (2023). Analysis Of The Acceleration Of Time And Cost Of Implementing Building Construction Projects Using The Critical Path Method (Cpm) Method. Journal of Research and Community Servis, 4(2), 336–346. https://devotion.greenvest.co.id/index.php/dev/article/view/388
Lugina, L., Agustian, S., & Geraldo, C. S. (2022). Penerapan Metode Project Evaluation adn Review Technique (PERT) dan Critical Path Method (CPM) terhadap Pembangunan Gedung. Jurnal Pendidikan Tambusai, 6(8), 880–888. https://jptam.org/index.php/jptam/article/view/3014
Mandiyo Priyo, M. R. A. (2015). Aplikasi Metode Time Cost Trade Off Pada Proyek Konstruksi : Studi Kasus Proyek Pembangunan Gedung Indonesia. JURNAL ILMIAH SEMESTA TEKNIKA, 18(1), 30–43. https://journal.umy.ac.id/index.php/st/article/view/703
Perdana, M. S. A., & Sari, R. P. (2022). Optimalisasi Waktu Pelaksanaan Proyek Konstruksi Rumah Tinggal Menggunakan Metode CPM (Critical Path Method) dan PERT (Program Evaluation and Review Technique). Jurnal Media Teknik & Sistem Industri, Vol. 6 (no(2), 116–123. https://doi.org/10.35194/jmtsi.v6i2.1944
Rizky Widyo Kisworo, Fajar Sri Handayani, S. (2017). Analisis Percepatan Proyek Menggunakan Metode Time Cost Trade Off Dengan Penambahan Jam Kerja Lembur Dan Jumlah Alat. E-Jurnal Matriks Teknik Sipil, (September 2017), 766–776. https://jurnal.uns.ac.id/matriks/article/view/36702
Sa, N., & Rijanto, T. (2021). Evaluasi Proyek Pembangunan Gedung Stroke Center (Paviliun Flamboyan) Menggunakan Metode Critical Path Method ( CPM ) Dan Crashing Evaluation of building construction Stroke Center (Paviliun Flamboyan) using the Critical Path Method ( CPM ) And Crashi. E-ISSN : 2655-6421, Desember 2(2), 55–62.
https://journal.unesa.ac.id/index.php/proteksi/article/view/15271
Safa’at. (2020). Analisis Network Planning Dengan Critical Path Method (Cpm) Dalam Usaha Efisiensi Waktu Pada Produksi Precast Di Pt Xyz. -, (6), 345–351. https://ojs.stiemahardhika.ac.id/index.php/mahardika/article/view/49
Santoso, A. (2020). Analisis Percepatan Pelaksanaan Pekerjaan Proyek Menggunakan Critical Path Method (Studi Kasus Pembangunan Pasar Baru Kota Probolinggo). -, 1–10. http://repository.untag-sby.ac.id/3056/
Tarman, Rikzan Bachrul Ulum, G. R. (2019). Penjadwalan Proyek Mini Market Dengan Menggunakan Metode Cpm (Critical Path Method) Dan Pert di Pt Indomarco Prismatama Scheduling Mini Market Projects Using CPM (Critical Path Method) And Pert Methods at PT Indomarco Prismatama. Jurnal Teknologika (Jurnal Teknik-Logika-Matematika), 2018, 1–11. https://jurnal.wastukancana.ac.id/index.php/teknologika/article/view/160
Venn Y. I. Ilwaru, Dorteus L. Rahakbauw, J. T. (2018). Penjadwalan Waktu Proyek Pembangunan Rumah Dengan Menggunakan CPM (Critical Path Method) Time Schedule Project Of Housing Development Using CPM (Criticalpath Method) (Study Case: Residential Development in Amahusu Village, Ambon City). Jurnal Ilmu Matematika Dan Terapan, 12(2), 61–68. https://ojs3.unpatti.ac.id/index.php/barekeng/article/view/617