COST AND TIME ANALYSIS USING EARNED VALUE METHOD IN ADMINISTRATION BUILDING CONTRUCTION PROJECT AT POLIJE CAMPUS
Main Article Content
Implementation of construction projects often faces delays in work completion. Delays in project completion that exceed the time limit specified in the contract cause losses both from the contractor as the executor and the assignor. Project implementers pay more attention to the cost aspects incurred and often ignore the time control of project implementation so that project implementation often experiences delays in work. The purpose of this study is to analyze the time efficiency carried out by the provider from the beginning of the work, during monitoring, to the end of the project implementation. And estimate how much it costs from the start of work, when monitoring until the project is completed using the Earned Value Method. From the analysis, results and discussion of the Bondowoso Polije Campus Administration Building project, it can be concluded that the project work time exceeds 2,543 weeks for the total work and will experience a loss of Rp 393,323,318.10 from the reduction of the total contract minus the total financing. Therefore, the construction management proposes to shift the work schedule to work that does not require the achievement of the main construction. In addition, the contractor should communicate to the assignor of the Administration Building project to increase the duration of the administrative building construction project work. And participate in finding alternative suppliers of the main material without having to wait for the vendor to get the material needed.
Ariana, I. K. A., & Lestari, D. A. (2023). Analisis Kinerja Proyek Optimalisasi SPAM Gatak Kabupaten Sukoharjo dengan Metode Earned Value. Journal of Integrated System, 6(1), 87–102.
Asnuddin, S., Tjakra, J., & Sibi, M. (2018). Penerapan Manajemen Konstruksi Pada Tahap Controlling Proyek.(Studi Kasus: Bangunan Laboratorium Fakultas Teknik Universitas Sam Ratulangi Manado). Jurnal Sipil Statik, 6(11).
Ayudya, I. I. M., Pratami, D., & Saputra, M. (2023). Perancangan Scope Baseline, Schedule Baseline Dan Performance Measurement Mengunakan Earned Value Method Pada Proyek Pengembangan Sistem Informasi Pendidikan Terintegrasi Universitas ABC. EProceedings of Engineering, 10(2).
Barrientos-Orellana, A., Ballesteros-Pérez, P., Mora-Melià, D., Cerezo-Narváez, A., & Gutiérrez-Bahamondes, J. H. (2023). Comparison of the Stability and Accuracy of Deterministic Project Cost Prediction Methods in Earned Value Management. Buildings, 13(5), 1206.
Dimyati, H., & Kadar, N. (2014). Manajemen Proyek: CV Pustaka Setia.
Ginting, J. V. B. G. (2020). Metode Earned Value Pada Pengendalian Proyek Pembangunan Gedung Sekolah SD Methodist-an Pancur Batu. ARBITRASE: Journal of Economics and Accounting, 1(1), 6–10.
Hendriyani, I., Pratiwi, R., & Qadri, N. (2020). Optimasi Waktu dan Biaya pada Pelaksanaan Proyek Peningkatan Jalan Bina Bakti Kelurahan Gunung Seteleng Kabupaten Penajam Paser Utara dengan Metode Time Cost Trade Off (TCTO): Time and Cost Optimization in The Implementation of the Improvement of the Bina Bakti Road of Gunung Seteleng Kabupaten Penajam Paser Utara with Time Cost Trade Off (TCTO) Method. Jurnal Ilmiah Teknik Sipil TRANSUKMA, 3(1), 65–76.
Husein, A., & Perencanaan, M. P. (2011). Penjadwalan, dan Pengendalian Proyek (Edisi Revisi). Yogyakarta: Andi Offset.
Ifeanyi, E. I. (2019). Quantitative Approach to Project Scope Change Management in Building Projects. PM World Journal, 3(4), 1–24.
Mangkunegara, A. P., & Prabu, A. (2005). Evaluasi kinerja sumber daya manusia. Bandung: Refika Aditama, 61–68.
Marleno, R., Surjokusumo, S., Oetomo, W., Setiawan, M. I., & Abdullah, D. (2018). The influence of stakeholder factors affecting the success of construction projects in Indonesia. Journal of Physics: Conference Series, 1114(1), 12135.
Marpaung, R., Daulay, I. N., & Tambunan, V. (n.d.). Optimalisasi penjadwalan proyek pembangunan pabrik kelapa sawit dengan menggunakan metode PERT dan CPM pada PT. Bintang Riski Abadi. SOROT, 17(2), 117–127.
Pranowo, D. A. (2007). Pengendalian Proyek dengan Metode Earned Value (Studi Kasus Proyek Rusunawa Universitas Diponegoro Semarang). Prodi Teknik Sipil UNIKA Soegijapranata.
Rahman, I. (2010). Earned value analysis terhadap biaya pada proyek pembangunan gedung. Surakarta: Universitas Sebelas Maret.
Salsabila, M. D. N., Puspita, I. A., & Widyasthana, S. (2022). The Project Performance Evaluation of PLBN Project Using Earned Value Management Method. International Journal of Innovation in Enterprise System, 6(01), 61–73.
Santoso, B. (2003). Manajemen Proyek. Guna Widya Anonim.
Soeharto, I. (1997). Manajemen proyek dari konseptual sampai operasional.
Soemardi, B. W., Abduh, M., & Reini & Pujoartanto, N. (2007). Konsep Earned Value untuk Pengelolaan Proyek Konstruksi, Buku Referensi, Konstruksi: Industri, Pengelolaan dan Rekayasa. Bandung: Penerbit ITB.
Wijanarko, B., & Oetomo, W. (2019). Analisis Percepatan Waktu Penyelesaian Proyek Dengan Metode Crashing Dan Fast Tracking Pada Pelebaran Jalan Dan Jembatan’. Jurnal Untag__.